Listed below are the upcoming major road works for the current year along with a brief description, anticipated duration of the works, and the rounded numbers of approved budget. The exact numbers can be found in our 2021 budget on page 17.

Please note that the approximate dates listed below are estimates and subject to change due to delays or other issues.

Alfred

Gravel Roads

Rang Saint Jean and Concession 7

Description: Adding gravel to Rang Saint Jean and Concession 7 between Ritchance Road and Peat Moss Road.

Approximate dates: June to September 2021

Approved budget: $50,150

Lefaivre

Guard rails

Concession 2 Lefaivre

Description: Adding a guard rail to the bridge on Concession 2 Lefaivre between Montée Ouellette and Boundary Road.

Approximate dates: September 2021

Approved budget: $35,000

Culverts

Concession 3 Lefaivre

Description: Replacing culverts between Bolt Road and County Road 15.

Approximate dates: June to September 2021

Approved budget: $20,000

Montée Honoré Lalonde

Description: Replacing a culvert between Concession 2 Lefaivre and Concession 3 Lefaivre.

Approximate dates: June to September 2021

Approved budget: $8,000

Plantagenet

Asphalt

Jessup's Falls Road

Description: Repaving Jessup's Falls Road.

Approximate dates: May to July 2021

Approved budget: $124,550

Parent Street

Description: Repaving Parent Street.

Approximate dates: May to July 2021

Approved budget: $31,600

Pitch-Off Road

Description: Repaving Pitch-Off Road.

Approximate dates: May to July 2021

Approved budget: $127,480

Culverts

Boundary Road (North)

Description: Replacement of culverts between Concession 4 and Concession 5

Approximate dates: June to September 2021

Approved budget: $13,000

Concession 4 Plantagenet

Description: Replacement of a culvert between County Road 9 and Boundary Road.

Approximate dates: June to September 2021

Approved budget: $16,000

Concession 5 Plantagenet

Description: Replacement of culverts between County Road 17 and the end of Concession 5.

Approximate dates: June to September 2021

Approved budget: $26,000

Concession 9 Plantagenet

Description: Replacement of a culvert near Cartier Road.

Approximate dates: June to September 2021

Approved budget: $9,000

Gravel Roads

Concession 7 Plantagenet

Description: Adding gravel between Road 11 and 14.

Approximate dates: June to September 2021

Approved budget: $50,150

Concession 9 Plantagenet

Description: Adding gravel between County Road 9 and the river, as well as between Cartier Road and Road 16.

Approximate dates: June to September 2021

Approved budget: $134,400

Concession 10 Plantagenet

Description: Adding gravel between County road 9 and the river.

Approximate dates: June to September 2021

Approved budget: $167,750

Guard Rails

Concession 9 Plantagenet

Description: Adding a guard rail between County Road 19 and County Road 2.

Approximate dates: September 2021

Approved budget: $40,000

Sidewalks

Village of Plantagenet

Description: Fixing the sidewalks of the village of Plantagenet, postponed project from 2020.

Approximate dates: June to September 2021

Approved budget: $188,850

Wendover

Asphalt

Principale Street (West)

Description: Repaving Principale Street West between civic address 3373 and Division Road.

Approximate dates: May to July 2021

Approved budget: $517,580

Gravel Roads

Concession 1 Wendover

Description: Adding gravel between Division Road and the end of Concession 1.

Approximate dates: June to September 2021

Approved budget: $10,760

Concession 2 Wendover

Description: Adding gravel between County Road 17 and County Road 19.

Approximate dates: June to September 2021

Approved budget: $87,560

Division Road

Description: Adding gravel between Concession 1 and Concession 2.

Approximate dates: June to September 2021

Approved budget: $50,000

Guard Rails

Principale Street

Description: Adding a guard rail near civic address 3033, postponed project from 2020.

Approximate dates: September 2021

Approved budget: $15,000